Notice of Road Work: Pinole Pavement Rehabilitation Project
City News
- October 6, 2026
NOTICE OF ROAD WORK – PINOLE PAVEMENT REHABILITATION PROJECT
Project Areas: Shea Drive, Pinole Valley Road, Marlesta Road
Construction Period: September 21 – October 31, 2026
Contractors: McGuire & Hester
Dear Residents,
The City of Pinole started performing important pavement rehabilitation work in your neighborhood. Work will take place over several weeks and may include milling, paving, iron adjustments, digouts, striping, and surface treatments on Mondays through Fridays. Please review the schedule below for your street.
Shea Drive (Pinole Valley Road to Sarah Drive) – Scheduled Work
• Week of 10/05: Speed bump Install
• Week of 10/12: Raising iron
• Week of 10/19: Final Striping
Pinole Valley Road (Pinole Valley Bridge to Simas Avenue) – Scheduled Work
• Week of 10/05: Dig Outs and Crack filling
• Week of 10/12: Crack filling and Slurry
• Week of 10/19: Striping
Marlesta Road (Appian Way to Marionola) – Scheduled Work
• Week of 10/05: Milling and FillingÂ
• Week of 10/12: Raise Iron
• Week of 10/19: Final Striping
What Residents Should Expect
• Temporary lane closures and slowed traffic
• Occasional driveway access delays during active paving
• Construction noise during standard work hours
• No‑parking zones will be posted in advance—please observe signage
Crews typically aim to complete major activities by Friday each week.
How You Can Help
• Remove vehicles from posted no‑parking areas
• Plan extra travel time during work periods
• Keep children and pets away from work zones
• Follow flagger and traffic control instructions
Contact Information
For questions or special access needs, please contact:
• City of Pinole Public Works – (510) 724‑9910
• Construction Contractor Field Office – (510) 632‑7676